Construction Change Order SOP Template

Document a requested scope change, estimate its cost and schedule impact, and record authorization before updating the project.

Template edition

Procedure overview

Construction Change Order

Process owner
Project manager
Trigger
A field condition or request changes the agreed scope.
Inputs
Original scope, written request or field notes, estimate, and schedule baseline.
See the procedure

Procedure preview

Use for administrative tracking of scope changes on an active construction project. Follow the project contract for approval authority and notice.

  1. Open a numbered change request

    Project coordinator

    Record the request, reason, date, and affected drawing, specification, or work package.

    Record Change request ID

  2. Assess the impact

    Estimator

    Record labor, materials, subcontractor costs, and any expected schedule movement.

    Record Cost and schedule estimate

  3. Review with the project team

    Project manager

    Confirm dependencies and document how the change affects committed work and the current schedule.

    Record Reviewed proposal

  4. Obtain authorization

    Project manager

    Route the proposal to the parties named in the contract and capture the version and decision.

    Record Authorization record

  5. Update project records

    Project coordinator

    Update the budget, schedule, and field instructions with the approved change and its effective date.

    Record Updated change log